John Hart: sudden short-circuit test support
Level 2 and 3 technical support for EnerOptim / BC Hydro.
John Hart generating station (BC Hydro), on the Campbell River, Vancouver Island, is rated 138 MW across three units of about 46 MW. FORWA provided on-site support for a sudden short-circuit commissioning test over more than 200 hours in July 2021, characterizing synchronous machine behaviour.
Highlights
- Sudden short-circuit test
- Level 2 and 3 technical services
- Support right at the station
Results
- Commissioning test completed properly
- Focused expertise deployed on-site