NETA preventive maintenance on 2GS, 4GS and Grinder Room for Portage Power.
During planned multidisciplinary outages at Victoria Island (Portage Power), FORWA handled the electrical scope over more than 600 hours: inspection and testing of electrical equipment, station service transformer testing, input and output verification, ASTM oil sampling and analysis, photographic records and witnessed test sheets, discrepancy follow-up and return to service.
Highlights
- Planned multidisciplinary outages
- More than 600 hours
- Inspection and testing of electrical equipment
- Station service transformer testing
- Input and output verification
- ASTM oil sampling and analysis
- Photographic records and witnessed test sheets
- Discrepancy follow-up and return to service
Results
- Electrical outage delivered in the planned window
- Confirmed maintenance partner