Calabogie: complete testing and commissioning of a hydroelectric redevelopment

From HV switching through to digital protection testing, for SNC-Sullivan / OPG.

Calabogie generating station (OPG), on the Madawaska River, has generated power since 1917. Its century-old powerhouse was replaced by a new station that roughly doubles capacity, from about 5 to about 11 MW. FORWA worked for SNC-Sullivan Joint Venture on complete testing and commissioning of the redevelopment. Over close to two years and nearly 3,000 hours: generator and auxiliary testing, outdoor substation testing and commissioning, 5 kV breaker and cable testing, generator and transformer protection (SEL-487E and T60 relays), teleprotection and communications validation, input/output verification, and isolation, lockout-tagout and re-energization procedures.

Highlights

  • Generator and auxiliary testing
  • Outdoor substation testing and commissioning
  • 5 kV breaker and cable testing
  • Generator and transformer protection
  • Teleprotection and communications validation
  • Input and output verification
  • Isolation, lockout-tagout and re-energization procedures

Results

  • Complete, safe commissioning
  • Hydro One connection milestones prepared

A comparable mandate?

Describe the asset, the role you need and the site window.

Discuss a similar project